Risk prioritization – Other parameters

Here is the sequence of steps for risk prioritization

  • Develop the risk register
  • Define the probability and impact scales
  • Assign probability and impact ratings to the risk
  • Perform qualitative risk analysis by prioritizing the risks based on their Probability x Impact value
  • Some of the other parameters used for risk prioritization are;
    • Difficulty in detection of the risk
    • Urgency – If certain risks are going to happen immediately, that must be factored into risk prioritization
  • Define thresholds – These are triggers for action
    • Project-wide thresholds could be established to involve senior management when product costs exceed 10 percent of the target cost or when cost performance indices (CPIs) fall below 0.95.
    • Schedule thresholds could be established to involve senior management when schedule performance indices (SPIs) fall below 0.95.
    • Performance thresholds could be established to involve senior management when specified key items (e.g., processor utilization, average response times) exceed 125 percent of the intended design.